COSHH 2002 LEV Thorough Examination & Testing (14-Month Rule)
Metalworking fluid mist, neat cutting oils, laser/weld fume, and grinding dust are hazardous substances under COSHH 2002 (SI 2002/2677). Regulation 9(2)(a) sets a strict 14-month ceiling for Thorough Examination and Testing (TExT)—unless Schedule 4 mandates 6 months or 1 month.
1. Statutory Intervals: 14 Months vs Schedule 4 Exceptions
Most CNC shops treat coolant-mist extraction as an annual 12-month booking so Competent Person scheduling never breaches the legal 14-month maximum under COSHH Reg 9(2)(a). However, Schedule 4 Column 1 imposes far shorter ceilings on severe-wear metal processes.
| COSHH Reference | Process / Plant Scope | Maximum Legal Interval |
|---|---|---|
| Reg 9(2)(a) | General CNC coolant-mist extractors, oil-smoke units, laser/weld fume LEV | At least every 14 months |
| Schedule 4 (6M) | Mechanical metal grinding, abrasion, or polishing (>12 hrs/week) & non-ferrous casting dust/fume | At least every 6 months |
| Schedule 4 (1M) | Abrasive blasting carried out in or incidental to cleaning metal castings | At least every 1 month |
2. What an HSG258 TExT Report Must Record
Under HSE HSG258 (Controlling airborne contaminants at work), an LEV Thorough Examination and Test is not a bare spreadsheet of airflow numbers. Your Competent Person (typically BOHS P601/P602 qualified) must evaluate current performance against the original commissioning baseline.
- System identity & branch map: linked machine enclosures, flexible ducts, blast gates, and Schedule 4 process flag.
- Commissioning baseline: design volumetric flow (m3/h), hood face velocity (m/s), capture velocity (m/s), and fan/filter static pressure (Pa).
- Quantitative airflow readings & smoke/tracer containment check confirming mist does not escape into the operator breathing zone.
- Explicit adequacy verdict and numbered defect schedule with rectification deadlines.
3. How ProCERT Models LEV-MIST-01 Utility Cascades
In real workshops, one central mist extractor (such as LEV-MIST-01) manifolds onto three or more CNC centres (VMC-01, VMC-02, LATHE-01). When LEV-MIST-01's certificate expires or an immediate_prohibition remedial is opened, ProCERT derives LOCKED_OUT and dependency_blocked = true live on every linked child machine.
Using probus-pdf-v1, your H&S Lead opens page 4 of the uploaded TExT PDF, draws a bounding box around Clause 4.1/4.2, and anchors the remedial directly to the inspector's exact words and coordinate box.
Shop-Floor Operational Checklist
- Verify whether dry grinding (>12 hrs/week) or casting fettling places any extractor onto Schedule 4 (6M or 1M) rather than 14M.
- Upload the original commissioning spec alongside every TExT PDF in your private tenant vault so face/capture velocity drops are visible.
- Link parent extractors to every downstream CNC centre in asset_dependencies so overdue LEV never leaves machines appearing cleared.
- Use 60 / 30 / 14 / 0-day reminders to book your Competent Person ahead of the 14-month ceiling and retain records for at least 5 years.